CMDP+ | Tunbridge Wells, Kent
Coleman was awarded Phase 2 of the Tunbridge Wells South Water Treatment Works project following its exceptional performance in the delivery of Phase 1.
Contract value: c£2.2m | Duration 1.5 years
This phase involved installing new equipment and upgrading existing systems to comply with revised environmental regulations and new permit requirements.
The project included a range of works such as building a large 24.5-metre reinforced concrete tank (“Final Settlement Tank”), improving the site’s inlet area, installing new pipelines and upgrading the pumping station. Coleman also laid new pipes and cables across the site and created strong concrete areas for equipment.
The Coleman team carried out major excavation works, built access roads, and installed new chambers, drainage and pipework. The new Final Settlement Tank represents the largest circular water-retaining structure that Coleman has delivered to date. The construction required a bespoke formwork system (temporary steel moulds to hold the wet concrete in shape until it hardens), which was assembled in sections and lifted into position by crane. Installing the associated pipework required careful planning, including temporary supports for existing pipes that were suspended while new ones were installed up to 6 metres deep.
The project is progressing well towards completion thanks to the strong collaboration among all contractors on site to maintain momentum. Focus is now on finishing the remaining works, restoring the site, and handing over a high-quality asset to our valued customer.
"Coleman delivered exceptional performance at Tunbridge Wells South UIMP5 project, which was complex and demanding. Despite numerous technical challenges and shifting requirements, they consistently demonstrated strong problem-solving skills and clear communication with a proactive approach. Their expertise, attention to detail and commitment to meeting deadlines were instrumental to keeping the project on track."
Jeff Tighe
Construction and Delivery Lead, CMDP+